FENX.05.05-IP.02-0033/26

Strzałka

Project title: Enhancing the technical capabilities of CARGOUNIT electric locomotives through the installation and upgrading of the ERTMS system

Project No.: FENX.05.05-IP.02-0033/26

Beneficiary: CARGOUNIT Spółka z ograniczoną odpowiedzialnością

Project location:

Company registered office: 54-207 Wrocław, ul. Na Ostatnim Groszu 3. The project will be carried out at the technical branch office in Zabrze, at Szkubacza Street 10, Building B3, 41-800. The locomotives will be used by intermodal operators operating in Poland and other EU countries.

Estimated total cost of implementing the Project [PLN]: 76 808 072,01

Maximum amount of eligible expenditure [PLN]: 62 395 587,00

Funding rate: 84%

Total amount of funding [PLN]: 52 412 293,08

Funding from national funds/as a specific-purpose grant [PLN]: not applicable

Funding in the form of payments [PLN]: 52 412 293,08

Aim of the project:

The project implements the objectives and principles of the FEnIKS 2021–2027 programme and SZOOP for the FEnIKS. The aim of the Project is to improve rail transport safety by installing and upgrading ETCS systems in 15 electric locomotives. This aim is in line with the aforementioned documents and will be achieved through the modernisation of locomotives intended for use on freight services.

Method of measuring the indicator:

Base value: 0 – the rolling stock has not yet been used for operational service on the ERTMS/ETCS system;

Target value: 1 180 000 – annual operational mileage covered by rolling stock fitted with the ERTMS/ETCS system as per the design, based on historical data (the product of the annual mileage (in thousands of km) of one locomotive of a given type and the number of such locomotives: 50×2 (111Eb); 100 × 3 (594-Traxx); 60 × 3 (E4DCUd); 80 × 3 (E6ACT); 90 × 4 (E6ACTa). Verification based on the annual operational performance summary and data from counters. Target year: 2030

Subject and scope of the project:

Cargounit Sp. z o.o. (hereinafter: Cargounit, the Applicant, the Company) plans to carry out a project involving the installation and upgrading of ETCS systems (in accordance with specification 4.0.0, version 2.1 or higher) in 15 electric locomotives, which are technically and legally adapted for operation and for carrying out freight journeys within Poland.

Task:

This is a procurement project involving the modernisation of the ERTMS system through the installation/upgrade of the ETCS system to specification 4.0.0, version 2.1 or higher, in 15 electric locomotives owned by Cargounit Sp. z o.o. The Global System for Mobile Railways (GSM-R) is already installed in the locomotives covered by the project. Prior to the commencement of the work, a tender procedure for the performance of the works was prepared and published in the Competitiveness Database.

The scope of the task includes:

• signing a contract with the systems supplier – planned by 31 January 2027 

• deliveries of systems for further locomotives, technical acceptance tests, certification, [1 February 2027 – 30 September 2029]

• interim payments and final settlement, project settlement [1 February 2027 – 31 December 2029]

• introduction of the modernized rolling stock into service – scheduled for 1 October 2029

The timetable has been drawn up considering the standard lead time for installation, software deployment and the necessary testing, which, based on market research and the Applicant’s own experience, is approximately 34 months.

The scope of the planned update covers:

• Sub-task 1.1 – Modernisation of CARGOUNIT Sp. z o.o.’s rolling stock, involving the fitting of the 111Eb rail vehicles (2 units) with the ERTMS system;

• Sub-task 1.2 – Modernisation of CARGOUNIT Sp. z o.o.’s rolling stock, involving the fitting of the ERTMS system to three E6ACT rail vehicles;

• Sub-task 1.3 – Modernisation of CARGOUNIT Sp. z o.o.’s rolling stock, involving the upgrade of the ERTMS system from version 2.3.0d to 4.0.0 on the E6ACTa rail vehicles (4 units);

• Sub-task 1.4 – Modernisation of CARGOUNIT Sp. z o.o.’s rolling stock, involving the upgrade of the ERTMS system from version 2.3.0d to 4.0.0 on the E4DCUd rail vehicles (3 units);

• Sub-task 1.5 – Modernisation of CARGOUNIT Sp. z o.o.’s rolling stock, involving the upgrade of the ERTMS system from version 3.4.0 to 4.0.0 on three TRAXX DC3 rail vehicles.

In particular, the activities will include:

• Carrying out an initial inspection of the locomotive to verify the equipment and wiring diagrams,

• Installation of the required ETCS components,

• Commissioning of the equipment and software,

• Final inspection/acceptance of the work carried out,

• Conversion and uploading of RBC keys,

• Carrying out RSC/ESC tests,

• Provision of all necessary documents and approvals for the ECM process,

• Certification (cost not exceeding 7 per cent of eligible costs)

Achieving the immediate objective will also facilitate the achievement of the objectives arising from the existing transport problem:

• Increasing the availability of modern rolling stock;

• Reducing the burden on road transport;

• Improvements in the energy and environmental efficiency of transport;

• Strengthening the potential of the intermodal transport market in Poland and Europe.

Irregularities:

How to report potential irregularities or misconduct in FEnIKS?

We would like to inform you about the mechanism enabling the reporting of potential irregularities or financial irregularities in projects co-financed under the European Funds for Infrastructure, Climate and the Environment 2021–2027 (FEnIKS) programme, which has been developed and made available by the programme’s Managing Authority.

Information regarding irregularities or financial fraud can be reported by sending an email to: naduzycia.feniks@epec.elblag.pl

More information: https://www.feniks.gov.pl/strony/dowiedz-sie-wiecej-o-programie/zglaszanie-nieprawidlowosci/

This mechanism is not a channel for making reports within the meaning of the Act of 14 June 2024 on the protection of whistleblowers (Journal of Laws, item 928) and is not intended for making reports within the meaning of that Act, but solely for reporting potential irregularities or financial irregularities in the Project being implemented, or as an IT tool enabling the submission of information regarding suspected irregularities or financial irregularities.

Reports of irregularities or financial irregularities will enable appropriate remedial measures to be taken and will help to ensure the highest standards in the implementation of projects in an ethical, open and transparent manner.

Please note that it is also possible to report to the Managing Authority, the Intermediate Body or the Implementing Authority any suspected non-compliance of a project or the Beneficiary’s activities with the Convention on the Rights of Persons with Disabilities (CRPD) or the Charter of Fundamental Rights (CFR). Reports, notifications or complaints regarding the Project’s non-compliance with the provisions of the KPP or KPON may be submitted by natural persons (project participants or their authorised representatives), institutions involved in the implementation of European Union funds, and civil society organisations (associations, foundations) by means of (in each of the following cases, the report shall be deemed to have been submitted in writing):

1) by post – in the form of a letter sent to the following address: Ministry of Funds and Regional Policy, ul. Wspólna 2/4, 00-926 Warsaw, or the Centre for EU Transport Projects, Plac Europejski 2, 00-844 Warsaw,

2) the ePUAP outbox of the Ministry of Funds and Regional Policy or via a public registered electronic delivery service or a public hybrid service, as referred to in the Act of 18 November 2020 on electronic deliveries (Journal of Laws of 2026, items 3 and 507),

3) the e-Irregularities online form, available on the website www.feniks.gov.pl,

4) a reporting mechanism, understood as a dedicated email address: rownosc.feniks@mfipr.gov.pl lub naduzycia.feniks@mfipr.gov.pl,

5) by hand delivery to the registry of the Ministry of Funds and Regional Policy, ul. Wspólna 2/4, 00-926 Warsaw, or to the registry of the Centre for EU Transport Projects, Plac Europejski 2, 00-844 Warsaw.

The principles we follow when considering the reports submitted to us:

1) to carry out a reliable assessment of the risk of fraud arising in connection with the implementation of the Project and to develop effective and proportionate measures to prevent fraud,

2) to document that a risk analysis of financial fraud has been carried out in connection with the implementation of the Project (in accordance with the template attached as an annex to the Guide on Combating Financial Fraud issued by the Managing Authority, or using the Beneficiary’s own tool). Where a Beneficiary is implementing more than one project under FEnIKS for which it is required to document the conduct of a financial fraud risk analysis, it will be sufficient to prepare a consolidated financial fraud risk analysis for those projects.